- Accessibility via PATCO to Franklin Square and adjacent neighborhoods, businesses, and attractions
- Installation of ADA compliant elevator, escalator, and ramps
- Relocation and replacement of decades-old water transmission line from under Franklin Square to run under 7th
- Construction of architectural headhouse
- Green roof to help condition space and manage stormwater runoff
- Skylight over stairs and transparent walls for daylighting and to emphasize the viewshed of Franklin Square Park
About the Project
Project Enhancements
Timeline
Task |
Timeframe |
---|---|
Total Project Duration | February 2022 to February 2024 |
Phase 1 – Water Main Relocation from Franklin Square Park to 7th Street | March 2022 to August 2022 |
Phase 2 – Construct Egress Headhouses along 6th Street | August 2022 to March 2023 |
Phase 3 – Construct Entrance Headhouse along 7th Street | September 2022 to February 2024 |