Date
|
Update
|
October 2022 |
- Completed plumbing demolition.
- Completed excavation of the entrance headhouse.
- Completed shoring at the entrance headhouse.
- Continued electrical rough in along Platforms I and II.
- Poured concrete walls for egress houses.
- Removed duct bank along entrance headhouse.
|
September 2022 |
- Completed excavation at egress headhouses.
- Completed testing and installation of micropiles at egress headhouse #2.
- Poured concrete foundation for egress headhouse #2.
- Began excavation of the entrance headhouse.
- Began shoring at the entrance headhouse.
|
August 2022 |
- Demobilized and removed MPT along 7th Street – Watermain work complete.
- Demolished tile and metal wall panels in the Concourse.
- Began electrical rough in work at Concourse and Platforms.
- Began excavation along 6th Street egress headhouses.
- Removed concrete cover, granite wall panels, and recessed stair treads at the 6th Street egress headhouses.
|
July 2022 |
- A new conduit rack has been installed on track 1.
- Road restoration is being prepared.
- Watermain pipe in to Race Street installed and completed.
- Water shutdown was completed for watermain pipe.
- The connection at Vine Street was completed.
|
June 2022 |
- Watermain pipe is installed successfully.
- Platform work is happening at night, with both platforms being power washed.
- Tactile edge work on platform 1 is ongoing and will last through July.
- Shoring and excavating for the entrance house has begun and will continue.
|
May 2022 |
- Bus shelter on 7th Street and Race Streets has been removed.
- Watermain pipe work has begun.
- Tree protection work completed with no issues.
- Security walls being installed to separate concourse from platforms.
- Approximately 30% of the water mainline is complete.
- Water line across 7th Street is complete.
- Temporary concourse walls are being installed on both platforms.
|
April 2022 |
- Traffic controls put in place overnight. Traffic is operating with no issues.
- Installed lateral tie-ins for inlets, two of three inlets are now completed.
- A track outage is successfully completed to run a temporary powerline through the station into an existing electrical room.
|
February 2022 |
Construction for the Franklin Square Station begins. |